| Schemes | Villages | < 50% Physical Progress | 51-75% Physical Progress | > 75% Physical Progress | Physically Completed Scheme | Financially Completed Scheme |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| 255 | 934 | 83 | 87 | 85 | 25 | 0 |
| Schemes | Village | RWS Village Status | ||
| Fully Functional | Partially Functional | Non Functional | ||
|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 |
| 5644 | 9886 | 1711 | 6208 | 1967 |
| Schemes | Villages | Physically Completed Scheme | Physically Completed Village | Financially Completed Scheme | Financially Completed Village | Physically Not Completed /WIP Schemes | Physically Not Completed /WIP Villages | Financialy Not Completed /WIP Schemes | financialy Not Completed /WIP Villags |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
|---|---|---|---|---|---|---|---|---|---|
| 3704 | 5547 | 3501 | 4914 | 1357 | 1910 | 94 | 588 | 2238 | 3655 |
| SNO | Phase | Total Schemes |
Total Villages Certified Village |
RWS Villages | Work Completed | Work In Progress | Villages in O&M but not RWS/No Disruption |
OHT | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Total RWS Villages RWS(%) |
100%
90% to 99% < 90% |
O&M SchemesVillages |
Trial Run SchemesVillages |
SchemesVillages |
Direct Pumping SchemesVillages |
No RWS SchemesVillages |
Required OHT | Completed OHT | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| 1 | Phase 1 | 63 | 6529 4567 | 5720 88% | 38967751049 | 44 3908 | 5 551 | 14 2078 | 0 0 | 13680 | 11 | 1699 | 1646 |
| 2 | Phase 2/3/5 |
36294 | 72442 13770 | 45131 62% | 20825850815798 | 9160 17087 | 6836 14007 | 20298 41979 | 819115328 | 1291125611 | 72 | 36442 | 19140 |
| 3 | Phase 4 | 14 | 6113 119 | 0 0% | 000 | 0 0 | 0 0 | 14 6113 | 00 | 14/6113 | 0 | 1818 | 173 |
| 4 | JJM total | 36371 | 85084 18456 | 50851 60% | 24721 9283 16847 | 9204 20995 | 6841 14558 | 20326 50170 | 8191 15328 | 12938 32404 | 83 | 39959 | 20959 |
| 5 | Jal Nigam (O&M Agency) | 5644 | 9886 8899 | 7919 80% | 17118995309 | 745 1284 | 0 0 | 0 0 | 00 | 0/0 | 439 | 0 | 0 |
| 6 | Total JJM+JAL Nigam | 42015 | 94970 27355 | 58770 62% | 26432 10182 22156 | 9949 22279 | 6841 14558 | 20326 50170 | 8191 15328 | 12938 32404 | 522 | 39959 | 20959 |
| SNO | Type | Total Schemes |
Total Villages Certified Village |
RWS Villages | Work Completed | Work In Progress | Villages in O&M but not RWS/No Disruption |
OHT | Financial Details (Lakh) | ||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Total RWS Villages RWS(%) |
100%
90% to 99% < 90% |
O&M SchemesVillages |
Trial Run SchemesVillages |
SchemesVillages |
Direct Pumping SchemesVillages |
No RWS SchemesVillages |
Required OHT | Completed OHT | Estimated Cost | Expenditure | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
| 1 | SINGLE VILLAGE SCHEME (JJM) | 16427 | 16408 3847 | 10806 66% | 508022943432 | 4485 4484 | 3105 3105 | 8837 8824 | 33933391 | 52555248 | 5 | 16304 | 8923 | 4588683.64 | 2727821.07 |
| 2 | SINGLE VILLAGE SCHEME (Jal Nigam) | 3728 | 3730 3441 | 2963 79% | 5113382114 | 497 497 | 0 0 | 0 0 | 00 | 00 | 10 | 0 | 0 | 202.45 | 112.20 |
| Total | 20155 | 20138 7288 | 13769 68% | 559126325546 | 4982 4981 | 3105 3105 | 8837 8824 | 33933391 | 52555248 | 15 | 16304 | 8923 | 4588886.09 | 2727933.27 | |
| S.No. | Phase | Total Villages | Total RWS Disruption | Theft Disruption | Power / Electrical Disruption | Tullu Pump Disruption | Road Widening Disruption | Damage Village Internal Works | Local Repairing Disruption | Total | Pending >15 Days |
|||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total | Resolved | Pending | Total | FIR Lodged | Resolved | Pending (Village) | Pending >15Days | Total | Resolved | Pending | Pending >15Days | Total | Resolved | Pending | Pending >15Days | Total | Resolved | Pending | Pending >15Days | Total | Resolved | Pending | Pending >15Days | Total | Resolved | Pending | Pending >15Days | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 |
| 1 | Phase 1 | 6529 | 2456 | 2234 | 222 | 61 | 7 | 60 | 1 | 1 | 1432 | 1413 | 17 | 11 | 38 | 38 | 0 | 0 | 451 | 280 | 170 | 161 | 378 | 372 | 6 | 3 | 96 | 71 | 24 | 19 | 216 | 192 |
| 2 | Phase 2,3,5 | 72442 | 3247 | 2643 | 604 | 1767 | 330 | 1573 | 192 | 177 | 228 | 193 | 35 | 34 | 36 | 29 | 6 | 6 | 471 | 254 | 203 | 213 | 326 | 261 | 49 | 58 | 419 | 333 | 81 | 84 | 546 | 517 |
| 3 | Phase 4 | 6113 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||||||||||||||||||||
| 4 | Jal Nigam | 9886 | 284 | 74 | 210 | 11 | 7 | 4 | 4 | 49 | 22 | 26 | 26 | 60 | 18 | 42 | 22 | 63 | 7 | 54 | 55 | 43 | 9 | 34 | 34 | 58 | 11 | 47 | 46 | 201 | 178 | |
| Total | 94970 | 5987 | 4951 | 1036 | 1839 | 337 | 1640 | 197 | 182 | 1709 | 1628 | 78 | 71 | 134 | 85 | 48 | 28 | 985 | 541 | 427 | 429 | 573 | 415 | 152 | 149 | 747 | 642 | 89 | 95 | 963 | 887 | |
| # | District/Village | Issue Type | Reported Date | Remark |
|---|---|---|---|---|
| 1 | Jhansi / Ninaura |
Road Widening
|
10-Jan-2024 | Pwd has damaged the pipeline from last 1.5 years and still not repaired it till now. |
| 2 | Jhansi / Arjar |
Road Widening
|
12-Jan-2024 | Pwd has damaged the pipeline from last 1.5 years and not repaired it till now. |
| 3 | Kushi Nagar / Pipra Khurd |
Road Widening
|
12-Jan-2024 | Water Supply hampered due to Road Widening.Approx .5 KM Pipe line Damged & 58 Nos FHTC |
| 4 | Jhansi / Rampura |
Road Widening
|
16-Jan-2024 | Pwd has damaged the pipeline from last 1.5 years and not repaired it till now |
| 5 | Sonbhadra / Maitapur |
Road Widening
|
27-Jul-2024 | ROAD WIDENING DAMAGE WATER PIPE LINE WAITING DEPARTMENT PERMISSION |
| 6 | Saharanpur / Jajwa |
Theft
|
24-Jun-2025 | सोलर पैनल एवं तार चोरी होने के कारण सप्लाई बंद थी l |
| 7 | Prayagraj / Tudihar |
Theft
|
10-Nov-2025 | Solar Theft Reported |
| 8 | Bareilly / Sahasia Hasainpur Mustqil |
Theft
|
08-Jan-2026 | Solar wire theft |
| 9 | Jaunpur / Baihari |
Theft
|
08-Jan-2026 | Solar Module Theft |
| 10 | Sant Kabeer Nagar / Netwapur |
Theft
|
08-Jan-2026 | 2 Nos Solar Module theft from site. |
| 11 | Kushi Nagar / Pokhar Bhinda |
Power/Electrical Issue
|
16-Feb-2024 | Regular Water supply in this village hampered due to Electrical Supply not avilable in this Village. |
| 12 | Kushi Nagar / Brindaban |
Power/Electrical Issue
|
20-Feb-2024 | Only Pole Erection done.Transformer not installed and Connection not Done .So Water Supply not in this Village. |
| 13 | Kushi Nagar / Banka Khas |
Power/Electrical Issue
|
02-Mar-2024 | Regular Water Supply hampered due to Electrical Supply not avilable in this Village. |
| 14 | Kushi Nagar / Parsa Ahatmali |
Power/Electrical Issue
|
02-Mar-2024 | Regular Water Supply hampered in this village due to electrical supply not avilable in this village. |
| 15 | Kushi Nagar / Parsadpur |
Power/Electrical Issue
|
02-Mar-2024 | Regular Water Supply in this village hampered due to Electrical Supply not avilable in this village. |
| 16 | Shravasti / Semaritarhar |
Tullu Pump
|
02-Dec-2025 | Pump has been repairing |
| 17 | Meerut / Sarurpur Khurd |
Tullu Pump
|
15-Dec-2025 | Regular water supply has been operational for over 2 years; however, some villagers have installed direct tullu pumps and removed FCVs from FHTCs, causing pressure issues. |
| 18 | Etawah / Karyawali |
Tullu Pump
|
24-Feb-2026 | DUE TO TUBEWELL FAIL WATER SUPPLY NOT RUNNING. |
| 19 | Etawah / Neware |
Tullu Pump
|
24-Feb-2026 | DUE TO TUBEWELL FAIL WATER SUPPLY NOT RUNNING. |
| 20 | Etawah / Manikpur Bisu |
Tullu Pump
|
24-Feb-2026 | DUE TO TUBEWELL FAIL WATER SUPPLY NOT RUNNING. |
| 21 | Kanpur Nagar / Jadepur Dhassa |
Local Repairing
|
19-Feb-2024 | Solar Materials Damaged By Unknown Persons |
| 22 | Kanpur Nagar / Maduri |
Local Repairing
|
10-Aug-2024 | Solar Materials Damaged By Unknown Persons |
| 23 | Shravasti / Shivpur Bankata |
Local Repairing
|
21-May-2025 | Solar Damage |
| 24 | Shravasti / Shivajot |
Local Repairing
|
21-May-2025 | Solar Damage |
| 25 | Shravasti / Mohmmadpur Raja |
Local Repairing
|
01-Jun-2025 | Solar Damage |
| 26 | Sant Kabeer Nagar / Mahadewa |
Damage Village Internal Works
|
21-Jun-2025 | 31 Rmt pipeline damaged by Local Villagers |
| 27 | Sant Kabeer Nagar / Bedo Khor |
Damage Village Internal Works
|
23-Jul-2025 | 175 Rmt pipeline damaged by Local GOVT. Body during road construction work. |
| 28 | Sant Kabeer Nagar / CHEAPUR |
Damage Village Internal Works
|
23-Jul-2025 | 175 Rmt pipeline damaged by Local GOVT. Body during road construction work. |
| 29 | Sant Kabeer Nagar / Dahrauli |
Damage Village Internal Works
|
23-Jul-2025 | 175 Rmt pipeline damaged by Local GOVT. Body during road construction work. |
| 30 | Sant Kabeer Nagar / Suraina |
Damage Village Internal Works
|
28-Jul-2025 | 15 Rmt pipeline damaged by Local Villagers |
| SNo. | Phase | Total Villages | Theft | Power Electrical Issue |
Tullu Pump |
Road Widening |
Damage Village Internal Works |
Local Repairing |
Total | Pending More Than 15 Days |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 |
| 1 | Phase 1 | 6529 | 1 | 17 | 0 | 84 | 15 | 4 | 119 | 98 |
| 2 | Phase 2,3,5 | 72442 | 57 | 1 | 2 | 40 | 32 | 22 | 145 | 134 |
| 3 | Phase 4 | 6113 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 4 | Jal Nigam | 9886 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 4 | Total | 94970 | 58 | 18 | 2 | 124 | 47 | 26 | 264 | 232 |
| SNo. | Phase | Total Villages | Certification | Jal Arpan | Jal Aklan | 100% Road Restoration Villages |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| 1 | Phase 1 | 6529 | 4567 | 902 | 3986 | 5729 |
| 2 | Phase 2,3,5 | 72442 | 13770 | 4009 | 14196 | 55453 |
| 3 | Phase 4 | 6113 | 119 | 0 | 129 | 57 |
| 4 | JJM total | 85084 | 18456 | 4911 | 18311 | 61239 |
| SNo. | Total No of Villages | No of Villages Where RPWSS Finalized | No of Villages Where RPWSS in Draft | No of Village RPWSS not Started | Finalized(%) |
|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 |
| 1 | 97070 | 94326 | 1119 | 1625 | 97.17% |
| Sr.No. | Components | Total | Phase 1 | Phase 2,3,5 | Phase 4 | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Target | Achivement | % | Target | Achivement | % | Target | Achivement | % | Target | Achivement | % | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| 1 | ट्यूबवेल | 38936 | 38540 | 98.98 | 550 | 550 | 100.00 | 38386 | 37990 | 98.97 | 0 | 0 | |
| 2 | पंप हाउस | 38936 | 37767 | 97.00 | 550 | 550 | 100.00 | 38386 | 37217 | 96.95 | 0 | 0 | |
| 3 | क्लोरीनीकरण प्रणाली | 38386 | 25403 | 66.18 | 0 | 0 | 38386 | 25403 | 66.18 | 0 | 0 | ||
| 4 | पाइपलाइन बिछाने का कार्य (कि.मी). | 564334 | 520806 | 92.29 | 58117 | 57458 | 98.87 | 450526 | 425957 | 94.55 | 55691 | 37391 | 67.14 |
| 5 | सौर ऊर्जा प्लांट | 32863 | 29024 | 88.32 | 0 | 0 | 32863 | 29024 | 88.32 | 0 | 0 | ||
| 6 | घरेलू नल कनेक्शन(FHTC) | 22331868 | 20259399 | 90.72 | 1685084 | 1670275 | 99.12 | 18888125 | 18245861 | 96.60 | 1758659 | 343263 | 19.52 |
| 7 | जल शुद्धिकरण संयंत्र (W.T.P) | 72 | 62 | 86.11 | 62 | 62 | 100.00 | 0 | 0 | 10 | 0 | 0.00 | |
| 8 | सड़क मरम्मत का कार्य (KM) | 201160 | 195405 | 97.14 | 10079 | 9678 | 96.02 | 181784 | 177110 | 97.43 | 9297 | 8617 | 92.69 |
| 9 | वे गाँव जहाँ 100% सड़क मरम्मत का कार्य पूर्ण हो चुका है। | 85471 | 61239 | 71.65 | 6547 | 5729 | 87.51 | 72795 | 55453 | 76.18 | 6129 | 57 | 0.93 |
| 10 | ओवरहेड टैंक (OHT) | 39959 | 38965/20959 | 97.51/52.45 | 1699 | 1684/1646 | 99.12/96.88 | 36442 | 35525/19140 | 97.48/52.52 | 1818 | 1756/173 | 96.59/9.52 |
| 11 | कमीशनिंग गाँव | 85471 | 52942 | 61.94 | 6547 | 6350 | 96.99 | 72795 | 46592 | 64.00 | 6129 | 0 | 0.00 |
| SNo. | Phase | Total | O&M | ||||
|---|---|---|---|---|---|---|---|
| Scheme | Integrated | Live | Scheme | Integrated | Live | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | Phase 1 | 63 | 54 | 51 | 44 | 43 | 43 |
| 2 | Phase 2,3,5 | 36297 | 10870 | 7270 | 9160 | 7775 | 5622 |
| 4 | JJM total | 36360 | 10924 | 7321 | 9204 | 7818 | 5665 |
| ## | Jal Nigam | 5644 | 0 | 0 | 0 | 0 | 0 |
| 4 | All total | 42004 | 10924 | 7321 | 9204 | 7818 | 5665 |
| SNo. | Phase | Total Complaint | O&M Complaint | ||||
|---|---|---|---|---|---|---|---|
| Total | Close | Pending | Total | Close | Pending | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | Phase 1 | 25485 | 21735 | 3750 | 16208 | 14806 | 1402 |
| 2 | Phase 2,3,5 | 80034 | 70547 | 9487 | 27143 | 24512 | 2631 |
| 3 | Phase 4 | 3085 | 2982 | 103 | 0 | 0 | 0 |
| 4 | Jal Nigam | 13684 | 12054 | 1630 | 3016 | 2442 | 574 |
| 4 | JJM total | 122288 | 107318 | 14970 | 46367 | 41760 | 4607 |
| Sno | Description | Total Villages | Completed Villages | Work In Progress Villages | Completed(%) |
|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 |
| 1 | Arsenic | 738 | 559 | 179 | 76 |
| 2 | Fluoride | 1460 | 886 | 574 | 61 |
| 3 | JE/AES | 1146 | 750 | 396 | 65 |
| S. No. | Test By | Test Details | ||||||
| Total Test | Village Tested | Safe found | Contaminated found | Remedial Action | Re-Test | Re-Test found Safe | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
|---|---|---|---|---|---|---|---|---|
UTTAR PRADESH FHTC PROGRESS