Go To District Dashboard
| SNO | Phase | Total Schemes |
Total Villages Certified Village |
RWS Villages | Work Completed | Work In Progress | Villages in O&M but not RWS |
OHT | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Total RWS Villages RWS(%) |
100%
90% to 99% < 90% |
O&M SchemesVillages |
Trial Run SchemesVillages |
SchemesVillages |
Direct Pumping SchemesVillages |
No RWS SchemesVillages |
Required OHT | Completed OHT | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| 1 | Phase 1 | 63 | 6530 4506 | 5331 82% | 311811381075 | 42 3806 | 7 654 | 14 2078 | 0 0 | 131059 | 28 | 1697 | 1645 |
| 2 | Phase 2/3/5 |
36286 | 72445 13408 | 40893 56% | 19087809113715 | 7235 13312 | 7306 14886 | 21745 44895 | 744413859 | 1482229393 | 102 | 36451 | 18357 |
| 3 | Phase 4 | 14 | 6191 177 | 39 1% | 0039 | 0 0 | 0 0 | 14 6191 | 00 | 14/6152 | 0 | 1818 | 134 |
| 4 | JJM total | 36363 | 85166 18091 | 46263 54% | 22205 9229 14829 | 7277 17118 | 7313 15540 | 21773 53164 | 7444 13859 | 14849 36604 | 130 | 39966 | 20136 |
| 5 | Jal Nigam | 5645 | 9862 8856 | 7591 77% | 16496925250 | 0 0 | 0 0 | 0 0 | 00 | 0/0 | 682 | 0 | 0 |
| 6 | Total JJM+JAL Nigam | 42008 | 95028 26947 | 53854 57% | 23854 9921 20079 | 7277 17118 | 7313 15540 | 21773 53164 | 7444 13859 | 14849 36604 | 812 | 39966 | 20136 |
| SNo. | Phase | Total RWS disruption(Village) | O&M RWS disruption(Village) | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Theft | Power Electrical Issue |
Tullu Pump |
Road Widening |
Damage Village Internal Works |
Local Repairing |
Total | Pending More Than 15 Days | Theft | Power Electrical Issue |
Tullu Pump |
Road Widening |
Damage Village Internal Works |
Local Repairing |
Total | Pending More Than 15 Days | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 |
| 1 | Phase 1 | 15 | 6 | 0 | 109 | 17 | 7 | 150 | 139 | 9 | 5 | 0 | 54 | 12 | 2 | 79 | 68 |
| 2 | Phase 2,3,5 | 461 | 38 | 7 | 155 | 114 | 43 | 797 | 668 | 84 | 2 | 3 | 29 | 50 | 9 | 170 | 117 |
| 3 | Phase 4 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 4 | JJM total | 476 | 44 | 7 | 264 | 131 | 50 | 947 | 807 | 93 | 7 | 3 | 83 | 62 | 11 | 249 | 185 |
| SNo. | Phase | Certification | Jal Arpan | Jal Aklan | RPWSS | 100% Road Restoration Villages |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| 1 | Phase 1 | 4495 | 52 | 0 | 0 | 5688 |
| 2 | Phase 2,3,5 | 13358 | 419 | 0 | 0 | 55134 |
| 3 | Phase 4 | 177 | 0 | 0 | 0 | 10 |
| 4 | JJM total | 18030 | 471 | 0 | 0 | 60832 |
| Sr.No. | Components | Total | Phase 1 | Phase 2,3,5 | Phase 4 | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Target | Achivement | % | Target | Achivement | % | Target | Achivement | % | Target | Achivement | % | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| 1 | ट्यूबवेल | 38940 | 38541 | 98.98 | 550 | 550 | 100.00 | 38390 | 37991 | 98.96 | 0 | 0 | |
| 2 | पंप हाउस | 38940 | 37806 | 97.09 | 550 | 550 | 100.00 | 38390 | 37256 | 97.05 | 0 | 0 | |
| 3 | क्लोरीनीकरण प्रणाली | 24930 | 22891 | 91.82 | 0 | 0 | 24930 | 22891 | 91.82 | 0 | 0 | ||
| 4 | ओवरहेड टैंक (OHT) | 39966 | 38945/20136 | 97.45 | 1697 | 1684/1645 | 99.23 | 36451 | 35520/18357 | 97.45 | 1818 | 1741/134 | 95.76 |
| 5 | पाइपलाइन बिछाने का कार्य (कि.मी). | 564400 | 519485 | 92.04 | 58096 | 57393 | 98.79 | 450570 | 425755 | 94.49 | 55734 | 36337 | 65.20 |
| 6 | सौर ऊर्जा प्लांट | 32868 | 28976 | 88.16 | 0 | 0 | 32868 | 28976 | 88.16 | 0 | 0 | ||
| 7 | घरेलू नल कनेक्शन(FHTC) | 22380224 | 20193958 | 90.23 | 1685261 | 1664920 | 98.79 | 18897608 | 18186019 | 96.23 | 1797355 | 343019 | 19.08 |
| 8 | जल शुद्धिकरण संयंत्र (W.T.P) | 62 | 62 | 100.00 | 62 | 62 | 100.00 | 0 | 0 | 0 | 0 | ||
| 9 | सड़क मरम्मत का कार्य (KM) | 201007 | 194978 | 97.00 | 10044 | 9472 | 94.31 | 181761 | 177117 | 97.44 | 9202 | 8389 | 91.16 |
| 10 | वे गाँव जहाँ 100% सड़क मरम्मत का कार्य पूर्ण हो चुका है। | 85576 | 60832 | 71.09 | 6548 | 5688 | 86.87 | 72821 | 55134 | 75.71 | 6207 | 10 | 0.16 |
| 11 | कमीशनिंग गाँव | 85576 | 51936 | 60.69 | 6548 | 6287 | 96.01 | 72821 | 45649 | 62.69 | 6207 | 0 | 0.00 |
| SNo. | Phase | Total | O&M | ||||
|---|---|---|---|---|---|---|---|
| Scheme | Integrated | Live | Scheme | Integrated | Live | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | Phase 1 | 63 | 54 | 51 | 42 | 41 | 40 |
| 2 | Phase 2,3,5 | 36290 | 9058 | 6264 | 7235 | 5956 | 4535 |
| 4 | JJM total | 36353 | 9112 | 6315 | 7277 | 5997 | 4575 |
| SNo. | Phase | Total Complaint | O&M Complaint | ||||
|---|---|---|---|---|---|---|---|
| Total | Close | Pending | Total | Close | Pending | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | Phase 1 | 21514 | 17807 | 3707 | 13766 | 12256 | 1510 |
| 2 | Phase 2,3,5 | 69466 | 58611 | 10855 | 19138 | 16700 | 2438 |
| 3 | Phase 4 | 2901 | 2827 | 74 | 0 | 0 | |
| 4 | JJM total | 93881 | 79245 | 14636 | 32904 | 28956 | 3948 |
| Sno | Description | Villages | Total no. of HHs as on 02.12.25 | Achievement (In Nos.) | Achievement (In %) |
|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 |
| 1 | Drought-prone and desert areas | 6,665 | 20,75,883 | 19,97,671 | 96.23% |
| 2 | JE / AES affected villages | 1,296 | 3,11,040 | 2,88,365 | 92.71% |
UTTAR PRADESH FHTC PROGRESS