Go To District Dashboard
| SNO | Phase | Total Schemes |
Total Villages Certified Village |
RWS Villages | Work Completed | Work In Progress | Villages in O&M but not RWS |
OHT | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Total RWS Villages RWS(%) |
100%
90% to 99% < 90% |
O&M SchemesVillages |
Trial Run SchemesVillages |
SchemesVillages |
Direct Pumping SchemesVillages |
No RWS SchemesVillages |
Required OHT | Completed OHT | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| 1 | Phase 1 | 63 | 6530 4506 | 5325 82% | 311411281083 | 42 3806 | 7 654 | 14 2078 | 0 0 | 131065 | 28 | 1697 | 1645 |
| 2 | Phase 2/3/5 |
36285 | 72445 13400 | 40530 56% | 18879791013741 | 7138 13131 | 7225 14685 | 21922 45271 | 742813813 | 1494829655 | 131 | 36451 | 18279 |
| 3 | Phase 4 | 14 | 6191 177 | 39 1% | 0039 | 0 0 | 0 0 | 14 6191 | 00 | 14/6152 | 0 | 1818 | 124 |
| 4 | JJM total | 36362 | 85166 18083 | 45894 54% | 21993 9038 14863 | 7180 16937 | 7232 15339 | 21950 53540 | 7428 13813 | 14975 36872 | 159 | 39966 | 20048 |
| 5 | Jal Nigam | 5645 | 9862 8856 | 7571 77% | 16416895241 | 0 0 | 0 0 | 0 0 | 00 | 0/0 | 680 | 0 | 0 |
| 6 | Total JJM+JAL Nigam | 42007 | 95028 26939 | 53465 56% | 23634 9727 20104 | 7180 16937 | 7232 15339 | 21950 53540 | 7428 13813 | 14975 36872 | 839 | 39966 | 20048 |
| SNo. | Phase | Total RWS disruption(Village) | O&M RWS disruption(Village) | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Theft | Power Electrical Issue |
Tullu Pump |
Road Widening |
Damage Village Internal Works |
Local Repairing |
Total | Pending More Than 15 Days | Theft | Power Electrical Issue |
Tullu Pump |
Road Widening |
Damage Village Internal Works |
Local Repairing |
Total | Pending More Than 15 Days | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 |
| 1 | Phase 1 | 15 | 6 | 0 | 100 | 12 | 7 | 137 | 126 | 9 | 5 | 0 | 45 | 7 | 2 | 66 | 58 |
| 2 | Phase 2,3,5 | 571 | 49 | 4 | 130 | 99 | 47 | 883 | 769 | 93 | 5 | 0 | 24 | 43 | 8 | 170 | 125 |
| 3 | Phase 4 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 4 | JJM total | 586 | 55 | 4 | 230 | 111 | 54 | 1020 | 895 | 102 | 10 | 0 | 69 | 50 | 10 | 236 | 183 |
| SNo. | Phase | Certification | Jal Arpan | Jal Aklan | RPWSS | 100% Road Restoration Villages |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| 1 | Phase 1 | 4495 | 52 | 0 | 0 | 5675 |
| 2 | Phase 2,3,5 | 13350 | 410 | 0 | 0 | 55070 |
| 3 | Phase 4 | 177 | 0 | 0 | 0 | 10 |
| 4 | JJM total | 18022 | 462 | 0 | 0 | 60755 |
| Sr.No. | Components | Total | Phase 1 | Phase 2,3,5 | Phase 4 | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Target | Achivement | % | Target | Achivement | % | Target | Achivement | % | Target | Achivement | % | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| 1 | ट्यूबवेल | 38940 | 38541 | 98.98 | 550 | 550 | 100.00 | 38390 | 37991 | 98.96 | 0 | 0 | |
| 2 | पंप हाउस | 38940 | 37809 | 97.10 | 550 | 550 | 100.00 | 38390 | 37259 | 97.05 | 0 | 0 | |
| 3 | क्लोरीनीकरण प्रणाली | 24925 | 22887 | 91.82 | 0 | 0 | 24925 | 22887 | 91.82 | 0 | 0 | ||
| 4 | ओवरहेड टैंक (OHT) | 39966 | 38935/20048 | 97.42 | 1697 | 1684/1645 | 99.23 | 36451 | 35512/18279 | 97.42 | 1818 | 1739/124 | 95.65 |
| 5 | पाइपलाइन बिछाने का कार्य (कि.मी). | 564400 | 519415 | 92.03 | 58096 | 57388 | 98.78 | 450570 | 425710 | 94.48 | 55734 | 36317 | 65.16 |
| 6 | सौर ऊर्जा प्लांट | 32868 | 28978 | 88.16 | 0 | 0 | 32868 | 28978 | 88.16 | 0 | 0 | ||
| 7 | घरेलू नल कनेक्शन(FHTC) | 22380224 | 20191025 | 90.22 | 1685261 | 1664395 | 98.76 | 18897608 | 18183611 | 96.22 | 1797355 | 343019 | 19.08 |
| 8 | जल शुद्धिकरण संयंत्र (W.T.P) | 62 | 62 | 100.00 | 62 | 62 | 100.00 | 0 | 0 | 0 | 0 | ||
| 9 | सड़क मरम्मत का कार्य (KM) | 200987 | 194944 | 96.99 | 10044 | 9472 | 94.31 | 181755 | 177112 | 97.45 | 9188 | 8360 | 90.99 |
| 10 | वे गाँव जहाँ 100% सड़क मरम्मत का कार्य पूर्ण हो चुका है। | 85576 | 60830 | 71.08 | 6548 | 5688 | 86.87 | 72821 | 55132 | 75.71 | 6207 | 10 | 0.16 |
| 11 | कमीशनिंग गाँव | 85576 | 51864 | 60.61 | 6548 | 6282 | 95.94 | 72821 | 45582 | 62.59 | 6207 | 0 | 0.00 |
| SNo. | Phase | Total | O&M | ||||
|---|---|---|---|---|---|---|---|
| Scheme | Integrated | Live | Scheme | Integrated | Live | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | Phase 1 | 63 | 54 | 51 | 42 | 41 | 39 |
| 2 | Phase 2,3,5 | 36289 | 8949 | 6394 | 7138 | 5853 | 4543 |
| 4 | JJM total | 36352 | 9003 | 6445 | 7180 | 5894 | 4582 |
| SNo. | Phase | Total Complaint | O&M Complaint | ||||
|---|---|---|---|---|---|---|---|
| Total | Close | Pending | Total | Close | Pending | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | Phase 1 | 21342 | 17491 | 3851 | 13665 | 11981 | 1684 |
| 2 | Phase 2,3,5 | 68506 | 57523 | 10983 | 18598 | 16190 | 2408 |
| 3 | Phase 4 | 2890 | 2807 | 83 | 0 | 0 | |
| 4 | JJM total | 92738 | 77821 | 14917 | 32263 | 28171 | 4092 |
| Sno | Description | Villages | Total no. of HHs as on 02.12.25 | Achievement (In Nos.) | Achievement (In %) |
|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 |
| 1 | Drought-prone and desert areas | 6,665 | 20,75,883 | 19,97,671 | 96.23% |
| 2 | JE / AES affected villages | 1,296 | 3,11,040 | 2,88,365 | 92.71% |
UTTAR PRADESH FHTC PROGRESS