| Total Scheme | Physically Completed Schemes | Under Construction (UC) Scheme Progress | |||||||
| Schemes | Villages | Schemes | Villages | Schemes | Villages | < 50% Physical Progress | 51-75% Physical Progress | > 75% Physical Progress | Financially Completed Scheme |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
|---|---|---|---|---|---|---|---|---|---|
| 1653 | 3860 | 1434 | 3020 | 219 | 856 | 53 | 103 | 63 | 0 |
| Schemes | Village | RWS Village Status | ||
| Fully Functional | Partially Functional | Non Functional | ||
|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 |
| 5645 | 9892 | +59 1782 | +19 6329 | 1781 |
| Schemes | Villages | Physically Completed Scheme | Physically Completed Village | Financially Completed Scheme | Financially Completed Village | Physically Not Completed /WIP Schemes | Physically Not Completed /WIP Villages | Financialy Not Completed /WIP Schemes | financialy Not Completed /WIP Villags |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
|---|---|---|---|---|---|---|---|---|---|
| 3704 | 5546 | 3499 | 4911 | 1357 | 1909 | 96 | 591 | 2238 | 3655 |
| Schemes | Villages | Physically Completed Scheme | Physically Completed Village | Financially Completed Scheme | Financially Completed Village | Physically Not Completed Schemes | Physically Not Completed Villages | Financialy Not Completed Schemes | financialy Not Completed Villags |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
|---|---|---|---|---|---|---|---|---|---|
| 420 | 1378 | 139 | 312 | 0 | 0 | 281 | 1066 | 420 | 1378 |
| S. No. | District | Total | Major Repairable | Minor Repairable(Partial Functional) | ||||||||||
| Total | Fully Functional | Work Started | Work Completed | Handed Over to GP | Total | Work Started | Work Completed | Handed Over to GP | Total | Work Started | Work Completed | Handed Over to GP | ||
| Grand Total | 7539 | 1763 | 1656 | 1376 | 380 | 3032 | 652 | 482 | 376 | 2739 | 1004 | 894 | 4 | |
| 1 | Agra | 6397 | 1422 | 1258 | 1205 | 377 | 2480 | 422 | 399 | 375 | 2490 | 836 | 806 | 2 |
| 2 | Firozabad | 741 | 341 | 106 | 25 | 0 | 282 | 48 | 3 | 0 | 118 | 58 | 22 | 0 |
| 3 | Mathura | 95 | 0 | 67 | 51 | 2 | 27 | 14 | 9 | 0 | 68 | 53 | 42 | 2 |
| 4 | Unnao | 306 | 0 | 225 | 95 | 1 | 243 | 168 | 71 | 1 | 63 | 57 | 24 | 0 |
| S. No. | District | Total | Major Repairable | Minor Repairable(Partial Functional) | ||||||||||
| Total | Fully Functional | Work Started | Work Completed | Handed Over to GP | Total | Work Started | Work Completed | Handed Over to GP | Total | Work Started | Work Completed | Handed Over to GP | ||
| No Record Found | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| S. No. | District | Total | Major Repairable | Minor Repairable(Partial Functional) | ||||||||||
| Total | Fully Functional | Work Started | Work Completed | Handed Over to GP | Total | Work Started | Work Completed | Handed Over to GP | Total | Work Started | Work Completed | Handed Over to GP | ||
| Grand Total | 148 | 0 | 135 | 112 | 0 | 124 | 112 | 92 | 0 | 23 | 23 | 20 | 0 | |
| 1 | Firozabad | 1 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 1 | 0 | 0 |
| 2 | Mathura | 26 | 0 | 14 | 9 | 0 | 26 | 14 | 9 | 0 | 0 | 0 | 0 | 0 |
| 3 | Unnao | 121 | 0 | 120 | 103 | 0 | 98 | 98 | 83 | 0 | 22 | 22 | 20 | 0 |
| SNO | Phase | Total Schemes |
SNA Onboarded Schemes | CIRP Timeline Exceeding Schemes |
Total Villages Certified Village |
RWS Villages | Work Completed | Work In Progress | Villages in O&M but not RWS/No Disruption |
OHT | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| SNA Onboarded Schemes | Villages | Bill Generated Scheme | Schemes | Villages |
Total RWS Villages RWS(%) |
100%
90% to 99% < 90% |
O&M SchemesVillages |
Trial Run SchemesVillages |
SchemesVillages |
Direct Pumping SchemesVillages |
No RWS SchemesVillages |
Required OHT | Completed OHT | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 |
| 1 | Phase 1 | 63 | 1 | 29 | 0 | 0 | 0 | 6529 +17 4597 | +14 5778 88% | 40327241022 | +0 44 3908 | +0 5 551 | 14 2078 | 0 0 | 13644 | 11 | 1699 | +0 1654 |
| 2 | Phase 2/3/5 |
36291 | 15859 | 20593 | 5473 | 3261 | 4589 | 72440 +192 14015 | +181 45639 63% | 21112853915988 | +162 9570 17862 | +-97 6615 13595 | 20106 41604 | 818515357 | 1269925184 | 76 | 36436 | +70 19305 |
| 3 | Phase 4 | 14 | 0 | 0 | 0 | 0 | 0 | 6113 +0 119 | +0 0 0% | 000 | +0 0 0 | +0 0 0 | 14 6113 | 00 | 14/6113 | 0 | 1818 | +2 177 |
| 4 | JJM total | 36368 | 15860 | 20622 | 5473 | 3261 | 4589 | 85082 +209 18731 | +195 51417 60% | 25144 9263 17010 | +162 9614 21770 | +-97 6620 14146 | 20134 49795 | 8185 15357 | 12726 31941 | 87 | 39953 | 21136 |
| 5 | Jal Nigam | 5864 | 0 | 0 | 0 | 0 | 0 | 10748 +6 8905 | +78 8111 75% | 17828985431 | 5645 9892 | 0 0 | 219 856 | 00 | 219/856 | 345 | 0 | +0 0 |
| 6 | Total JJM+JAL Nigam | 42232 | 15860 | 20622 | 5473 | 3261 | 4589 | 95830 +215 27636 | +273 59528 62% | 26926 10161 22441 | 15259 31662 | 6620 14146 | 20353 50651 | 8185 15357 | 12945 32797 | 432 | 39953 | 21136 |
| SNO | Type | Total Schemes |
JJM Cost(without Inadmissible)(Cr) | Expenditure(Cr) | Balance(Cr) | SNA Onboarded Schemes | CIRP Timeline Exceeding Schemes |
Total Villages Certified Village |
RWS Villages | Work Completed | Work In Progress | Villages in O&M but not RWS/No Disruption |
OHT | Financial Details (Lakh) | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total Schemes | Bill Generated Scheme | Sanction Number Generated Amount(Cr) |
Total RWS Villages RWS(%) |
100%
90% to 99% < 90% |
O&M SchemesVillages |
Trial Run SchemesVillages |
SchemesVillages |
Direct Pumping SchemesVillages |
No RWS SchemesVillages |
Required OHT | Completed OHT | Estimated Cost | Expenditure | |||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 |
| 1 | SINGLE VILLAGE SCHEME (JJM) | 16425 | 44806.13 | 27206.84 | 17599.89 | 13065 | 5450 | 871.34 | 2726 | 16406 3892 | 10913 67% | 515122973465 | 4681 4680 | 3000 3000 | 8744 8731 | 33723370 | 51605153 | 4 | 16303 | 9020 | 4588657.15 | 2727821.07 |
| 2 | SINGLE VILLAGE SCHEME (Jal Nigam) | 3722 | 0.00 | 0.00 | 0.00 | 0 | 0 | 0.00 | 0 | 3724 3435 | 3012 81% | 5193382155 | 497 497 | 0 0 | 0 0 | 00 | 00 | 9 | 0 | 0 | 202.45 | 112.20 |
| Total | 20147 | 44806.13 | 27206.84 | 17599.89 | 13065 | 5450 | 871.34 | 2726 | 20130 7327 | 13925 69% | 567026355620 | 5178 5177 | 3000 3000 | 8744 8731 | 33723370 | 51605153 | 13 | 16303 | 9020 | 4588859.60 | 2727933.27 | |
| S.No. | Phase | Total Villages | Total RWS Disruption | Theft Disruption | Power / Electrical Disruption | Tullu Pump Disruption | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total | Resolved | Pending | Total | FIR Lodged | Resolved | Pending (Village) | Pending >15Days | Total | Resolved | Pending | Pending >15Days | Total | Resolved | Pending | Pending >15Days | |||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 |
| 1 | Phase 1 | 6529 | 2533 | 2401 | 132 | 61 | 7 | 60 | 1 | 1 | 1465 | 1453 | 12 | 10 | 38 | 38 | 0 | 0 |
| 2 | Phase 2,3,5 | 72440 | 3268 | 3130 | 138 | 1770 | 331 | 1738 | 32 | 27 | 228 | 227 | 1 | 1 | 36 | 36 | 0 | 0 |
| 3 | Phase 4 | 6113 | 0 | 0 | 0 | 0 | ||||||||||||
| 4 | Jal Nigam | 10748 | 285 | 160 | 125 | 11 | 10 | 1 | 1 | 49 | 32 | 16 | 17 | 60 | 27 | 33 | 13 | |
| Total | 95830 | 6086 | 5691 | 395 | 1842 | 338 | 1808 | 34 | 29 | 1742 | 1712 | 29 | 28 | 134 | 101 | 33 | 13 | |
| S.No. | Phase | Total Villages | Total RWS Disruption | Road Widening Disruption | Damage Village Internal Works | Local Repairing Disruption | Total | Pending >15 Days |
|||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total | Resolved | Pending | Total | Resolved | Pending | Pending >15Days | Total | Resolved | Pending | Pending >15Days | Total | Resolved | Pending | Pending >15Days | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 |
| 1 | Phase 1 | 6529 | 2533 | 2401 | 132 | 485 | 384 | 100 | 93 | 382 | 378 | 4 | 3 | 102 | 88 | 14 | 13 | 131 | 119 |
| 2 | Phase 2,3,5 | 72440 | 3268 | 3130 | 138 | 488 | 399 | 88 | 84 | 326 | 322 | 4 | 3 | 420 | 408 | 12 | 12 | 136 | 125 |
| 3 | Phase 4 | 6113 | 0 | 0 | 0 | 0 | 0 | 0 | |||||||||||
| 4 | Jal Nigam | 10748 | 285 | 160 | 125 | 63 | 30 | 33 | 32 | 43 | 31 | 12 | 12 | 59 | 30 | 29 | 29 | 120 | 99 |
| Total | 95830 | 6086 | 5691 | 395 | 1036 | 813 | 221 | 209 | 581 | 526 | 55 | 54 | 751 | 731 | 20 | 18 | 387 | 343 | |
| # | District/Village | Issue Type | Reported Date | Remark |
|---|---|---|---|---|
| 1 | Jhansi / Ninaura |
Road Widening
|
10-Jan-2024 | Pwd has damaged the pipeline from last 1.5 years and still not repaired it till now. |
| 2 | Jhansi / Arjar |
Road Widening
|
12-Jan-2024 | Pwd has damaged the pipeline from last 1.5 years and not repaired it till now. |
| 3 | Jhansi / Rampura |
Road Widening
|
16-Jan-2024 | Pwd has damaged the pipeline from last 1.5 years and not repaired it till now |
| 4 | Sonbhadra / Maitapur |
Road Widening
|
27-Jul-2024 | ROAD WIDENING DAMAGE WATER PIPE LINE WAITING DEPARTMENT PERMISSION |
| 5 | Sonbhadra / Guradah |
Road Widening
|
27-Jul-2024 | ROAD WIDENING DAMAGE WATER PIPE LINE WAITING DEPARTMENT PERMISSION |
| 6 | Jaunpur / Baihari |
Theft
|
08-Jan-2026 | Solar Module Theft |
| 7 | Maharajganj / Piparriya Guru Govind Ray |
Theft
|
13-Jan-2026 | Solar module has been theft by unknown person |
| 8 | Shravasti / Bagwani |
Theft
|
15-Jan-2026 | All Electrical equipment damage and theft. |
| 9 | Balrampur / KALYANPUR |
Theft
|
15-Jan-2026 | Stolen of Solar cable Inverter and Instrument cable. |
| 10 | Sant Kabeer Nagar / Nawadiha |
Theft
|
22-Jan-2026 | DIDF Vertical Pipes theft from site. |
| 11 | Farrukhabad / Baglakhula |
Power/Electrical Issue
|
01-Jul-2026 | BAGLAKHULA T/W power connection apply but estimate not received yet from Electrical Department. |
| 12 | Banda / Chak Takuli |
Power/Electrical Issue
|
07-Jul-2026 | Continuous low voltage received at Sikhlodi pump house. |
| 13 | Banda / Adharori |
Power/Electrical Issue
|
07-Jul-2026 | Continuous low voltage received at Sikhlodi pump house. |
| 14 | Banda / Bisanda (rural) |
Power/Electrical Issue
|
07-Jul-2026 | Continuous low voltage received at Sikhlodi pump house. |
| 15 | Banda / Punahur |
Power/Electrical Issue
|
07-Jul-2026 | Continuous low voltage received at Sikhlodi pump house. |
| 16 | Sant Kabeer Nagar / Dahrauli |
Local Repairing
|
23-Jul-2025 | During the ongoing drain construction work being executed by the local government body, the pipeline has been damaged, resulting in approximately 175 meters of damage. |
| 17 | Sant Kabeer Nagar / Parmeswarpur |
Local Repairing
|
23-Jul-2025 | During the ongoing drain construction work being executed by the local government body, the pipeline has been damaged, resulting in approximately 175 meters of damage. |
| 18 | Sant Kabeer Nagar / Suraina |
Local Repairing
|
28-Jul-2025 | During the ongoing house foundation construction work being carried out by local villagers, the pipeline was damaged, resulting in approximately 15 meters of damage. |
| 19 | Mahoba / Pachpahara |
Local Repairing
|
02-Feb-2026 | trauma center Contractor damaged Pipe Line and shifting work is in progress. |
| 20 | Jalaun / Phulella |
Local Repairing
|
01-Apr-2026 | Damaged by the UPPCL sub-agency during electrical pole erection work. Due to this issue, regular water supply could not be provided to the villagers. |
| 21 | Sant Kabeer Nagar / CHEAPUR |
Damage Village Internal Works
|
23-Jul-2025 | 175 Rmt pipeline damaged by Local GOVT. Body during road construction work. |
| 22 | Sonbhadra / Amawar |
Damage Village Internal Works
|
05-Sep-2025 | Damage to DI 350mm K9 Rising Main (WTP to Bagharu GLR-02) Further, the Rising Main line of DI 350mm K9 from WTP to Bagharu GLR-02 has been significantly damaged due to excavation activities executed by the UPPCL Department for pole erection. The contractor engaged by UPPCL carried out drilling without prior intimation or approval, thereby violating standard coordination protocols. The contractor has refused to undertake repairs, which is unacceptable. |
| 23 | Sonbhadra / Joru Khar |
Damage Village Internal Works
|
01-Nov-2025 | Damage to DI 250mm K9 Pipeline (Jorukhar Zone) Approximately 12 meters of DI 250mm K9 pipeline (Chainage: Jampani to Jorukhar) laid in Jorukhar Village has been severely damaged due to excavation activities undertaken by the Irrigation Department for canal construction along the same alignment. Multiple sections have been disturbed, with pipes displaced or discarded. Based on inspection, the damage is attributable to the bucket teeth of backhoe/excavators deployed during excavation. |
| 24 | Balrampur / Gondawa |
Damage Village Internal Works
|
28-Jan-2026 | Gondwa: 110 mm & 140 mm pipelines – Damaged by Road Department This has resulted in: Damage to existing road infrastructure Leakage and disruption in water supply Additional repair and restoration work required |
| 25 | Balrampur / Chulahbhari |
Damage Village Internal Works
|
29-Jan-2026 | Chulhabhari: 140 mm pipeline – Damaged by Panchayat Raj Department This has resulted in: Damage to existing road infrastructure Leakage and disruption in water supply Additional repair and restoration work required |
| SNo. | Phase | Total Villages | Theft | Power Electrical Issue |
Tullu Pump |
Road Widening |
Damage Village Internal Works |
Local Repairing |
Total | Pending More Than 15 Days |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 |
| 1 | Phase 1 | 6529 | 1 | 12 | 0 | 60 | 7 | 3 | 83 | 76 |
| 2 | Phase 2,3,5 | 72440 | 8 | 0 | 0 | 16 | 4 | 1 | 29 | 25 |
| 3 | Phase 4 | 6113 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 4 | Jal Nigam | 10748 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 4 | Total | 95830 | 9 | 12 | 0 | 76 | 11 | 4 | 112 | 101 |
| SNo. | Phase | Total Villages | HGJ Reported Villages | Certification | Jal Arpan | Jal Aklan | 100% Road Restoration Villages | Last Month VWSC Meeting | Current Month VWSC Meeting |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| 1 | Phase 1 | 6529 | 4962 | 4597 | 1311 | 3986 | 5740 | 0 | 0 |
| 2 | Phase 2,3,5 | 72440 | 21998 | 14015 | 5596 | 14196 | 55476 | 0 | 0 |
| 3 | Phase 4 | 6113 | 210 | 119 | 0 | 129 | 57 | 0 | 0 |
| 4 | Jal Nigam | 9892 | 9312 | 8905 | 296 | 8442 | 0 | 0 | 0 |
| # | Total | 94974 | 36482 | 27636 | 7203 | 26753 | 61273 | 0 | 0 |
| SNo. | Total No of Villages | No of Villages Where RPWSS Finalized | No of Villages Where RPWSS in Draft | No of Village RPWSS not Started | Finalized(%) |
|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 |
| 1 | 97070 | 94326 | 1119 | 1625 | 97.17% |
| Sr.No. | Components | Total | Phase 1 | Phase 2,3,5 | Phase 4 | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Target | Achivement | % | Target | Achivement | % | Target | Achivement | % | Target | Achivement | % | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| 1 | ट्यूबवेल | 38933 | 38538 | 98.99 | 550 | 550 | 100.00 | 38383 | 37988 | 98.97 | 0 | 0 | |
| 2 | पंप हाउस | 38933 | 37780 | 97.04 | 550 | 550 | 100.00 | 38383 | 37230 | 97.00 | 0 | 0 | |
| 3 | क्लोरीनीकरण प्रणाली | 38383 | 25583 | 66.65 | 0 | 0 | 38383 | 25583 | 66.65 | 0 | 0 | ||
| 4 | पाइपलाइन बिछाने का कार्य (कि.मी). | 564301 | 521168 | 92.36 | 58117 | 57467 | 98.88 | 450493 | 426011 | 94.57 | 55691 | 37690 | 67.68 |
| 5 | सौर ऊर्जा प्लांट | 32858 | 29044 | 88.39 | 0 | 0 | 32858 | 29044 | 88.39 | 0 | 0 | ||
| 6 | घरेलू नल कनेक्शन(FHTC) | 22331665 | 20296975 | 90.89 | 1685084 | 1671574 | 99.20 | 18887922 | 18281119 | 96.79 | 1758659 | 344282 | 19.58 |
| 7 | जल शुद्धिकरण संयंत्र (W.T.P) | 72 | 62 | 86.11 | 62 | 62 | 100.00 | 0 | 0 | 10 | 0 | 0.00 | |
| 8 | सड़क मरम्मत का कार्य (KM) | 202364 | 195541 | 96.63 | 10079 | 9695 | 96.19 | 182980 | 177192 | 96.84 | 9305 | 8654 | 93.00 |
| 9 | वे गाँव जहाँ 100% सड़क मरम्मत का कार्य पूर्ण हो चुका है। | 85461 | 61273 | 71.70 | 6547 | 5740 | 87.67 | 72785 | 55476 | 76.22 | 6129 | 57 | 0.93 |
| 10 | ओवरहेड टैंक (OHT) | 39953 | 38964/21136 | 97.52/52.90 | 1699 | 1683/1654 | 99.06/97.35 | 36436 | 35524/19305 | 97.50/52.98 | 1818 | 1757/177 | 96.64/9.74 |
| 11 | कमीशनिंग गाँव | 85461 | 53044 | 62.07 | 6547 | 6359 | 97.13 | 72785 | 46685 | 64.14 | 6129 | 0 | 0.00 |
| SNo. | Phase | Total | O&M | ||||
|---|---|---|---|---|---|---|---|
| Scheme | Integrated | Live | Scheme | Integrated | Live | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | Phase 1 | 63 | 53 | 42 | 44 | 42 | 35 |
| 2 | Phase 2,3,5 | 36295 | 11202 | 7741 | 9571 | 8183 | 6146 |
| 4 | JJM total | 36358 | 11255 | 7783 | 9615 | 8225 | 6181 |
| ## | Jal Nigam | 5864 | 0 | 0 | 0 | 0 | 0 |
| 4 | All total | 42222 | 11255 | 7783 | 9615 | 8225 | 6181 |
| SNo. | Phase | Total Complaint | O&M Complaint | ||||
|---|---|---|---|---|---|---|---|
| Total | Close | Pending | Total | Close | Pending | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | Phase 1 | 25942 | 22309 | 3633 | 16496 | 15194 | 1302 |
| 2 | Phase 2,3,5 | 81665 | 73219 | 8446 | 28777 | 26500 | 2277 |
| 3 | Phase 4 | 3120 | 3044 | 76 | 0 | 0 | 0 |
| 4 | Jal Nigam | 14009 | 12511 | 1498 | 3089 | 2526 | 563 |
| 4 | JJM total | 124736 | 111083 | 13653 | 48362 | 44220 | 4142 |
| Sno | Description | Total Villages | Completed Villages | Work In Progress Villages | Completed(%) |
| 1 | 2 | 3 | 4 | 5 | 6 |
|---|---|---|---|---|---|
| 1 | Arsenic | 738 | 562 | 176 | 76 |
| 2 | Fluoride | 1460 | 918 | 542 | 63 |
| 3 | JE/AES | 1146 | 753 | 393 | 66 |
| S. No. | Test By | Test Details | Contaminated Test Scheme Details | ||||||||||
| Total Test | Village Tested | Safe found | Contaminated found | Remedial Action | Re-Test | Re-Test found Safe | Village Without Scheme | Village With Scheme | O&M Scheme Village | Trial Run Scheme Village | Under Construction Scheme Village | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Arsenic Parameter test | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 2 | Fluoride Parameter test | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 3 | Other Parameter test | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 4 | Total | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |