Go To District Dashboard
| Total | O&M | Under Construction (UC) | Village Status | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Schemes | Villages | Schemes | Villages | No. RWS | Schemes | Villages | < 50% Physical Progress | 51-75% Physical Progress | > 75% Physical Progress | Fully Functional | Partially Functional | Non Functional |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 |
| 10011 | 10429 | 9753 | 9926 | 2579 | 258 | 936 | 83 | 91 | 84 | 1748 | 5639 | 3042 |
| SNO | Phase | Total Schemes |
Total Villages Certified Village |
RWS Villages | Work Completed | Work In Progress | Villages in O&M but not RWS/No Disruption |
OHT | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Total RWS Villages RWS(%) |
100%
90% to 99% < 90% |
O&M SchemesVillages |
Trial Run SchemesVillages |
SchemesVillages |
Direct Pumping SchemesVillages |
No RWS SchemesVillages |
Required OHT | Completed OHT | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| 1 | Phase 1 | 63 | 6529 4536 | 5673 87% | 38177961060 | 44 3908 | 5 551 | 14 2078 | 0 0 | 13727 | 13 | 1699 | 1646 |
| 2 | Phase 2/3/5 |
36288 | 72442 13649 | 44635 62% | 20673843215530 | 8842 16438 | 7010 14371 | 20436 42268 | 818915293 | 1310825986 | 91 | 36448 | 18973 |
| 3 | Phase 4 | 14 | 6191 177 | 39 1% | 0039 | 0 0 | 0 0 | 14 6191 | 00 | 14/6152 | 0 | 1818 | 168 |
| 4 | JJM total | 36365 | 85162 18362 | 50347 59% | 24490 9228 16629 | 8886 20346 | 7015 14922 | 20464 50537 | 8189 15293 | 13135 32865 | 104 | 39965 | 20787 |
| 5 | Jal Nigam (O&M Agency) | 5646 | 9909 8902 | 7800 79% | 18047965200 | 0 0 | 0 0 | 0 0 | 00 | 0/0 | 548 | 0 | 0 |
| 6 | Total JJM+JAL Nigam | 42011 | 95071 27264 | 58147 61% | 26294 10024 21829 | 8886 20346 | 7015 14922 | 20464 50537 | 8189 15293 | 13135 32865 | 652 | 39965 | 20787 |
| S.No. | Phase | Total RWS Disruption | Theft Disruption | Power / Electrical Disruption | Tullu Pump Disruption | Road Widening Disruption | Damage Village Internal Works | Local Repairing Disruption | Total | Pending >15 Days |
|||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total | Resolved | Pending | Total | FIR Lodged | Resolved | Pending (Village) | Pending >15Days | Total | Resolved | Pending | Pending >15Days | Total | Resolved | Pending | Pending >15Days | Total | Resolved | Pending | Pending >15Days | Total | Resolved | Pending | Pending >15Days | Total | Resolved | Pending | Pending >15Days | ||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 |
| 1 | Phase 1 | 2305 | 2069 | 236 | 48 | 7 | 47 | 1 | 1 | 1321 | 1303 | 18 | 18 | 38 | 35 | 3 | 3 | 434 | 254 | 178 | 124 | 375 | 369 | 6 | 4 | 89 | 61 | 27 | 26 | 230 | 174 |
| 2 | Phase 2,3,5 | 3221 | 2494 | 727 | 1751 | 314 | 1516 | 233 | 223 | 226 | 185 | 41 | 41 | 35 | 29 | 6 | 6 | 468 | 229 | 220 | 234 | 324 | 256 | 52 | 63 | 417 | 279 | 130 | 122 | 659 | 627 |
| 3 | Phase 4 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |||||||||||||||||||||
| JJM Total | 5526 | 4563 | 963 | 1799 | 321 | 1563 | 234 | 224 | 1547 | 1488 | 59 | 59 | 73 | 64 | 9 | 9 | 902 | 483 | 398 | 358 | 506 | 340 | 157 | 148 | 699 | 625 | 58 | 67 | 889 | 801 | |
| # | District/Village | Issue Type | Reported Date | Remark |
|---|---|---|---|---|
| 1 | Jhansi / Ninaura |
Road Widening
|
10-Jan-2024 | Pwd has damaged the pipeline from last 1.5 years and still not repaired it till now. |
| 2 | Jhansi / Arjar |
Road Widening
|
12-Jan-2024 | Pwd has damaged the pipeline from last 1.5 years and not repaired it till now. |
| 3 | Kushi Nagar / Pipra Khurd |
Road Widening
|
12-Jan-2024 | Water Supply hampered due to Road Widening.Approx .5 KM Pipe line Damged & 58 Nos FHTC |
| 4 | Jhansi / Rampura |
Road Widening
|
16-Jan-2024 | Pwd has damaged the pipeline from last 1.5 years and not repaired it till now |
| 5 | Hardoi / MAJHRETA |
Road Widening
|
15-Jun-2024 | 1300 Mtr HDPE Pipe Damaged |
| 6 | Bareilly / Rajpur Kalan |
Theft
|
02-Jan-2026 | Solar wire theft |
| 7 | Bareilly / Khailamdeh Jageer |
Theft
|
07-Jan-2026 | Solar wire theft |
| 8 | Bareilly / Sahasia Hasainpur Mustqil |
Theft
|
08-Jan-2026 | Solar wire theft |
| 9 | Jaunpur / Baihari |
Theft
|
08-Jan-2026 | Solar Module Theft |
| 10 | Sant Kabeer Nagar / Netwapur |
Theft
|
08-Jan-2026 | 2 Nos Solar Module theft from site. |
| 11 | Kushi Nagar / Chandarpur |
Power/Electrical Issue
|
16-Feb-2024 | Regular water supply hampered in this village due to Electrical supply not avilable in this vill;age. |
| 12 | Kushi Nagar / Sahuadih |
Power/Electrical Issue
|
16-Feb-2024 | Regular water supply hampered in this village due to Electrical supply not avilable in this vill;age. |
| 13 | Kushi Nagar / Pokhar Bhinda |
Power/Electrical Issue
|
16-Feb-2024 | Regular Water supply in this village hampered due to Electrical Supply not avilable in this Village. |
| 14 | Kushi Nagar / Balkudia |
Power/Electrical Issue
|
16-Feb-2024 | Regular Water Supply hampered due to Service Cable not Connected to Transformer. |
| 15 | Kushi Nagar / Sisai Dadhich |
Power/Electrical Issue
|
20-Feb-2024 | Transformer not Charged thruogh Electrical Supply.Other Work also pending.So Water in this village is not Regular. |
| 16 | Shravasti / Semaritarhar |
Tullu Pump
|
02-Dec-2025 | Pump has been repairing |
| 17 | Meerut / Sarurpur Khurd |
Tullu Pump
|
15-Dec-2025 | Regular water supply has been operational for over 2 years; however, some villagers have installed direct tullu pumps and removed FCVs from FHTCs, causing pressure issues. |
| 18 | Etawah / Karyawali |
Tullu Pump
|
24-Feb-2026 | DUE TO TUBEWELL FAIL WATER SUPPLY NOT RUNNING. |
| 19 | Etawah / Neware |
Tullu Pump
|
24-Feb-2026 | DUE TO TUBEWELL FAIL WATER SUPPLY NOT RUNNING. |
| 20 | Etawah / Manikpur Bisu |
Tullu Pump
|
24-Feb-2026 | DUE TO TUBEWELL FAIL WATER SUPPLY NOT RUNNING. |
| 21 | Kanpur Nagar / Jadepur Dhassa |
Local Repairing
|
19-Feb-2024 | Solar Materials Damaged By Unknown Persons |
| 22 | Kanpur Nagar / Maduri |
Local Repairing
|
10-Aug-2024 | Solar Materials Damaged By Unknown Persons |
| 23 | Prayagraj / Mohammadpur Sarai Ali |
Local Repairing
|
16-Mar-2025 | Solar Damaged, Repairing WIP |
| 24 | Shravasti / Shivpur Bankata |
Local Repairing
|
21-May-2025 | Solar Damage |
| 25 | Shravasti / Shivajot |
Local Repairing
|
21-May-2025 | Solar Damage |
| 26 | Bahraich / Parwani Gauri |
Damage Village Internal Works
|
15-Apr-2025 | Pipe line damaged by gram pradhan in making internal roads,due to this regular supply interrupted |
| 27 | Sant Kabeer Nagar / Mahadewa |
Damage Village Internal Works
|
21-Jun-2025 | 31 Rmt pipeline damaged by Local Villagers |
| 28 | Sant Kabeer Nagar / Bedo Khor |
Damage Village Internal Works
|
23-Jul-2025 | 175 Rmt pipeline damaged by Local GOVT. Body during road construction work. |
| 29 | Sant Kabeer Nagar / CHEAPUR |
Damage Village Internal Works
|
23-Jul-2025 | 175 Rmt pipeline damaged by Local GOVT. Body during road construction work. |
| 30 | Sant Kabeer Nagar / Dahrauli |
Damage Village Internal Works
|
23-Jul-2025 | 175 Rmt pipeline damaged by Local GOVT. Body during road construction work. |
| SNo. | Phase | Theft | Power Electrical Issue |
Tullu Pump |
Road Widening |
Damage Village Internal Works |
Local Repairing |
Total | Pending More Than 15 Days |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| 1 | Phase 1 | 1 | 18 | 3 | 93 | 19 | 5 | 136 | 116 |
| 2 | Phase 2,3,5 | 71 | 2 | 2 | 43 | 58 | 24 | 190 | 177 |
| 3 | Phase 4 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 4 | JJM total | 72 | 20 | 5 | 136 | 77 | 29 | 326 | 293 |
| SNo. | Phase | Total Villages | Certification | Jal Arpan | Jal Aklan | RPWSS | 100% Road Restoration Villages |
|---|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | Phase 1 | 6529 | 4536 | 707 | 0 | 0 | 5717 |
| 2 | Phase 2,3,5 | 72442 | 13649 | 2998 | 0 | 0 | 55377 |
| 3 | Phase 4 | 6191 | 177 | 0 | 0 | 0 | 57 |
| 4 | JJM total | 85162 | 18362 | 3705 | 0 | 0 | 61151 |
| Sr.No. | Components | Total | Phase 1 | Phase 2,3,5 | Phase 4 | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Target | Achivement | % | Target | Achivement | % | Target | Achivement | % | Target | Achivement | % | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| 1 | ट्यूबवेल | 38937 | 38540 | 98.98 | 550 | 550 | 100.00 | 38387 | 37990 | 98.97 | 0 | 0 | |
| 2 | पंप हाउस | 38937 | 37760 | 96.98 | 550 | 550 | 100.00 | 38387 | 37210 | 96.93 | 0 | 0 | |
| 3 | क्लोरीनीकरण प्रणाली | 38387 | 25148 | 65.51 | 0 | 0 | 38387 | 25148 | 65.51 | 0 | 0 | ||
| 4 | पाइपलाइन बिछाने का कार्य (कि.मी). | 564340 | 520601 | 92.25 | 58117 | 57454 | 98.86 | 450532 | 425951 | 94.54 | 55691 | 37196 | 66.79 |
| 5 | सौर ऊर्जा प्लांट | 32864 | 29017 | 88.29 | 0 | 0 | 32864 | 29017 | 88.29 | 0 | 0 | ||
| 6 | घरेलू नल कनेक्शन(FHTC) | 22373491 | 20293932 | 90.71 | 1685084 | 1670275 | 99.12 | 18891052 | 18244365 | 96.58 | 1797355 | 379292 | 21.10 |
| 7 | जल शुद्धिकरण संयंत्र (W.T.P) | 72 | 62 | 86.11 | 62 | 62 | 100.00 | 0 | 0 | 10 | 0 | 0.00 | |
| 8 | सड़क मरम्मत का कार्य (KM) | 201140 | 195353 | 97.12 | 10079 | 9648 | 95.72 | 181764 | 177088 | 97.43 | 9297 | 8617 | 92.69 |
| 9 | वे गाँव जहाँ 100% सड़क मरम्मत का कार्य पूर्ण हो चुका है। | 85548 | 61151 | 71.48 | 6547 | 5717 | 87.32 | 72794 | 55377 | 76.07 | 6207 | 57 | 0.92 |
| 10 | ओवरहेड टैंक (OHT) | 39965 | 38960/20787 | 97.49/52.01 | 1699 | 1684/1646 | 99.12/96.88 | 36448 | 35521/18973 | 97.46/52.05 | 1818 | 1755/168 | 96.53/9.24 |
| 11 | कमीशनिंग गाँव | 85548 | 52852 | 61.78 | 6547 | 6345 | 96.91 | 72794 | 46507 | 63.89 | 6207 | 0 | 0.00 |
| SNo. | Phase | Total | O&M | ||||
|---|---|---|---|---|---|---|---|
| Scheme | Integrated | Live | Scheme | Integrated | Live | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | Phase 1 | 63 | 54 | 47 | 44 | 43 | 38 |
| 2 | Phase 2,3,5 | 36291 | 10482 | 6937 | 8842 | 7399 | 5332 |
| 4 | JJM total | 36354 | 10536 | 6984 | 8886 | 7442 | 5370 |
| SNo. | Phase | Total Complaint | O&M Complaint | ||||
|---|---|---|---|---|---|---|---|
| Total | Close | Pending | Total | Close | Pending | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | Phase 1 | 24868 | 20977 | 3891 | 15851 | 14329 | 1522 |
| 2 | Phase 2,3,5 | 77968 | 68239 | 9729 | 25520 | 22920 | 2600 |
| 3 | Phase 4 | 3090 | 3009 | 81 | 0 | 0 | |
| 4 | JJM total | 105926 | 92225 | 13701 | 41371 | 37249 | 4122 |
| Sno | Description | Total Villages | Completed Villages | Work In Progress Villages | Completed(%) |
|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 |
| 1 | Arsenic | 738 | 559 | 179 | 76 |
| 2 | Fluoride | 1460 | 886 | 574 | 61 |
| 3 | JE/AES | 1146 | 750 | 396 | 65 |
UTTAR PRADESH FHTC PROGRESS