Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Etah
AGENCY Power Mech Projects Ltd
SCHEME ID 20007377
SCHEME NAME RAMNAGAR SOHAR
ESTIMATED COST 345.00
EXPENDITURE 176.11
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 2
Boring Done 2
Air Compressor Done 2
O.P. Unit Done 2
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 32
Procured 32 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 10403.00 Meter
Length Laid 10403.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Etah Sakit Daspur 399817 Daspur 118 116 98% Work In Progress Not Certified
2 Etah Sakit Daspur 399818 Jaitpur 153 152 99% Work In Progress Not Certified
3 Etah Sakit RAMNAGAR SONHAR 399819 RAMNAGAR SONHAR 446 445 100% Work In Progress Not Certified
4 Etah Sakit RAMNAGAR SONHAR 399820 NOORPUR 130 127 98% Work In Progress Not Certified