Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Gorakhpur
AGENCY NCC Ltd.
SCHEME ID 20010880
SCHEME NAME BADAULI
ESTIMATED COST 259.30
EXPENDITURE 86.30
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 22
Procured 20 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 8345.00 Meter
Length Laid 6554.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Gorakhpur Sahjanwa Baidauli 455057 Baidauli 176 172 98% Work In Progress Not Certified
2 Gorakhpur Sahjanwa Baidauli 455058 Jagnal Digar 25 20 80% Work In Progress Not Certified
3 Gorakhpur Sahjanwa Baidauli 455059 Sidhauli 140 140 100% Har Ghar Jal Not Certified