Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Jaunpur
AGENCY Welspun Kaveri Infraprojects JV
SCHEME ID 20010939
SCHEME NAME Bhikhapur
ESTIMATED COST 478.88
EXPENDITURE 252.75
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 37
Procured 37 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 29075.00 Meter
Length Laid 29075.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Jaunpur Mugra Badshahpur Bhikhapur 469461 Chak Mathiya 64 63 98% Work In Progress Not Certified
2 Jaunpur Mugra Badshahpur Bhikhapur 469462 Bhikhapur 716 713 100% Work In Progress Not Certified