Scheme Details
DISTRICT
Gorakhpur
AGENCY
NCC Ltd.
SCHEME ID
20010944
SCHEME NAME
jabraila biskhore
ESTIMATED COST
330.95
EXPENDITURE
324.86
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
26
Procured
26
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14185.00
Meter
Length Laid
13000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Sahjanwa | Jabraila Bibikhore | 455036 | Jabraila Biskhore | 175 | 175 | 100% | Har Ghar Jal | Not Certified |
| 2 | Gorakhpur | Sahjanwa | Jabraila Bibikhore | 455037 | Jagal Aual | 42 | 40 | 95% | Work In Progress | Not Certified |
| 3 | Gorakhpur | Sahjanwa | Jabraila Bibikhore | 455038 | Rautpur | 93 | 89 | 96% | Work In Progress | Not Certified |
| 4 | Gorakhpur | Bansgaon | Baghrayee | 456089 | Baghrayee | 436 | 436 | 100% | Har Ghar Jal | Not Certified |