Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Bulandshahr | Welspun Kaveri Infraprojects JV | 20011221 | Chathehra Nityanandpur nagli Shakarpur WSS | 330.86 | 168.98 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Bulandshahr | Unchagaon | Chatehra | 393561 | Chatehra | 182 | 182 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Bulandshahr | Unchagaon | Nittyanandpur Nagli | 393563 | Nittyanandpur Nagli | 215 | 213 | 99 | Work In Progress | Not Certified | Not Verified |
3 | Bulandshahr | Unchagaon | Shakarpur | 393564 | Shakarpur | 124 | 119 | 96 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 24 | 24 | Yes | 0 | NA | No | 11881.00 | 11487.00 |