Scheme Details
DISTRICT
Raebareli
AGENCY
NCC Ltd.
SCHEME ID
20011286
SCHEME NAME
Dumatahar GP Water Supply Scheme
ESTIMATED COST
356.05
EXPENDITURE
184.55
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
25
Procured
25
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14569.65
Meter
Length Laid
14155.64
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Raebareli | Khiro | Dumather | 416971 | Dumarher | 564 | 554 | 98% | Work In Progress | Not Certified |