Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Aligarh
AGENCY ION EXCHANGE
SCHEME ID 20011361
SCHEME NAME Deta Saidpur
ESTIMATED COST 370.99
EXPENDITURE 138.94
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 30
Procured 30 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 14061.00 Meter
Length Laid 13700.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Aligarh Chandaus Deta Saidpur 394443 Deta Saidpur 524 521 99% Work In Progress Not Certified
2 Aligarh Chandaus Deta Saidpur 394444 Balrampur 125 125 100% Har Ghar Jal Not Certified
3 Aligarh Chandaus Deta Saidpur 394445 Majoopur 59 59 100% Har Ghar Jal Not Certified