Scheme Details
DISTRICT
Aligarh
AGENCY
ION EXCHANGE
SCHEME ID
20011519
SCHEME NAME
Hayatpur Hingotia
ESTIMATED COST
222.10
EXPENDITURE
101.32
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6453.10
Meter
Length Laid
7650.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Aligarh | Lodha | Hayatpur Hingotia | 394544 | Hayatpur Hingotia | 259 | 259 | 100% | Har Ghar Jal | Not Certified |
| 2 | Aligarh | Lodha | Hayatpur Hingotia | 394545 | Karilia | 236 | 236 | 100% | Har Ghar Jal | Not Certified |