Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Hardoi | NCC Ltd. | 20011901 | BARI | 292.05 | 212.34 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 23 | 23 | Yes | 0 | NA | No | 17267.00 | 17267.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | Shahabad | Bari | 411948 | Bari | 162 | 162 | 100 | Har Gar Jal | Certified |
| 2 | Hardoi | Shahabad | Bari | 411949 | Hazipur | 32 | 32 | 100 | Har Gar Jal | Certified |
| 3 | Hardoi | Shahabad | Bari | 411950 | GANUAPUR | 85 | 85 | 100 | Har Gar Jal | Certified |
| 4 | Hardoi | Shahabad | Bari | 411951 | HARDASPUR | 100 | 100 | 100 | Har Gar Jal | Certified |
| 5 | Hardoi | Shahabad | Bari | 411952 | Rahi | 30 | 30 | 100 | Har Gar Jal | Certified |