Scheme Details
DISTRICT
Mainpuri
AGENCY
NCC Ltd.
SCHEME ID
20012065
SCHEME NAME
BILLON VILLAGE WATER SUPPLY SCHEME
ESTIMATED COST
299.95
EXPENDITURE
132.06
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8097.00
Meter
Length Laid
7658.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mainpuri | Sultanganj | Billon | 400437 | Billon | 560 | 557 | 99% | Work In Progress | Not Certified |