Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Hardoi
AGENCY NCC Ltd.
SCHEME ID 20012343
SCHEME NAME Tavakkalpur
ESTIMATED COST 517.54
EXPENDITURE 431.06
AUTOMATION STATUS
Disconnected View Live Screen
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 37
Procured 37 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 24680.00 Meter
Length Laid 24680.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Hardoi Pihani Tavakkalpur 412110 Tavakkalpur 653 653 100% Har Ghar Jal Certified
2 Hardoi Pihani Tavakkalpur 412111 RASULAPUR 338 338 100% Har Ghar Jal Certified