Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Approve By Agency Status Approve By EE Status Automation Status
1 Hardoi NCC Ltd. 20012350 Parihawa Shekhpur 330.75 247.96 Verified Verified Not Integrated

Scheme Assigne Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified Handed Over Villages
1 Hardoi Sandila PARIHAWAN SHEKHWAPUR 413553 PARIHAWAN 292 292 100 Har Gar Jal Certified Verified
2 Hardoi Sandila PARIHAWAN SHEKHWAPUR 413554 SHEKHWAPUR 116 116 100 Har Gar Jal Certified Verified
3 Hardoi Sandila PARIHAWAN SHEKHWAPUR 413555 MAWAI BRAHMNAN 88 88 100 Har Gar Jal Certified Verified

Scheme Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
3 1 1 1 1 1 0 1 23 23 Yes 0 NA No 11185.00 11185.00