Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Hardoi | NCC Ltd. | 20012484 | Khanigawan Khurd | 430.88 | 270.71 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 30 | 30 | Yes | 0 | NA | No | 23773.00 | 23773.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | Shahabad | Khanigawan Khurd | 411840 | Khanigawan Khurd | 189 | 189 | 100 | Har Gar Jal | Certified | 
| 2 | Hardoi | Shahabad | Khanigawan Khurd | 411841 | Palthua | 200 | 200 | 100 | Har Gar Jal | Certified | 
| 3 | Hardoi | Shahabad | Khanigawan Khurd | 411842 | MAHAMMADPUR | 54 | 54 | 100 | Har Gar Jal | Certified | 
| 4 | Hardoi | Shahabad | Khanigawan Khurd | 411843 | Fattepur | 50 | 50 | 100 | Har Gar Jal | Certified | 
| 5 | Hardoi | Shahabad | Khanigawan Khurd | 411844 | Jamalpur | 108 | 108 | 100 | Har Gar Jal | Certified |