Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Etah
AGENCY Power Mech Projects Ltd
SCHEME ID 20012752
SCHEME NAME MIHUTA
ESTIMATED COST 252.46
EXPENDITURE 142.33
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 20
Procured 20 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 8884.00 Meter
Length Laid 9014.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Etah Aliganj Mihuta 399290 Mihuta 236 235 100% Work In Progress Not Certified
2 Etah Aliganj Mihuta 399291 Galarpur 123 122 99% Work In Progress Not Certified