Scheme Details
DISTRICT
Etah
AGENCY
Power Mech Projects Ltd
SCHEME ID
20012828
SCHEME NAME
REWAARI
ESTIMATED COST
301.57
EXPENDITURE
150.32
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
32
Procured
32
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
7013.00
Meter
Length Laid
10028.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etah | Sakit | Rewaari | 399756 | Rewaari | 406 | 405 | 100% | Work In Progress | Not Certified |
| 2 | Etah | Sakit | Rewaari | 399757 | Sakatpur Sakeet | 81 | 81 | 100% | Har Ghar Jal | Not Certified |