Scheme Details
DISTRICT
Etah
AGENCY
Power Mech Projects Ltd
SCHEME ID
20012990
SCHEME NAME
MIBARIKPUR
ESTIMATED COST
366.61
EXPENDITURE
210.28
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
40
Procured
40
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10404.00
Meter
Length Laid
9860.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etah | Sakit | Mubarikpur Sarai | 399763 | Mubarikpur Sarai | 230 | 230 | 100% | Har Ghar Jal | Not Certified |
| 2 | Etah | Sakit | Mubarikpur Sarai | 399764 | Rasakpur | 91 | 91 | 100% | Har Ghar Jal | Not Certified |
| 3 | Etah | Sakit | Mubarikpur Sarai | 399765 | Sadarpur | 143 | 141 | 99% | Work In Progress | Not Certified |
| 4 | Etah | Sakit | Mubarikpur Sarai | 399766 | Dugarpur | 78 | 78 | 100% | Har Ghar Jal | Not Certified |