Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Sitapur
AGENCY Larsen & Toubro Ltd
SCHEME ID 20013020
SCHEME NAME Parei Raipur water supply scheme
ESTIMATED COST 282.63
EXPENDITURE 169.37
AUTOMATION STATUS
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 1
Solar Plant
Required 21
Procured 21 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 9333.00 Meter
Length Laid 10254.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Sitapur Ealliya Perai Raipur 410266 Andauli 169 169 100% Har Ghar Jal Certified
2 Sitapur Ealliya Perai Raipur 410267 Chathiya 111 111 100% Har Ghar Jal Certified
3 Sitapur Ealliya Perai Raipur 410268 Perai Raipur 211 211 100% Har Ghar Jal Certified
4 Sitapur Behta Auri Shahpur 410733 Aureeshahpur 358 339 95% Work In Progress Not Certified