Scheme Details
DISTRICT
Sitapur
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20013024
SCHEME NAME
Aladpur water supply scheme
ESTIMATED COST
247.93
EXPENDITURE
124.03
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
25
Procured
25
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6010.00
Meter
Length Laid
6010.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Sidhauli | Aladadpur | 411713 | Aladadpur | 511 | 505 | 99% | Work In Progress | Not Certified |
| 2 | Sitapur | Sidhauli | Aladadpur | 411714 | Dharampur | 73 | 66 | 90% | Work In Progress | Not Certified |