Scheme Details
DISTRICT
Sitapur
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20013129
SCHEME NAME
Bahera Kuthehra water supply scheme
ESTIMATED COST
260.53
EXPENDITURE
153.87
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
14
Procured
14
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12755.00
Meter
Length Laid
12755.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Laharpur | Behra Kudehra | 410653 | Bahera Kuthehara | 196 | 193 | 98% | Work In Progress | Not Certified |
| 2 | Sitapur | Laharpur | Behra Kudehra | 410654 | Bhagauteepur | 173 | 170 | 98% | Work In Progress | Not Certified |