Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Hardoi | NCC Ltd. | 20013193 | SIKANDAR PUR | 237.35 | 174.74 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Hardoi | Sursa | SIKANDARPUR | 413008 | SIKANDARPUR | 130 | 130 | 100 | Har Gar Jal | Certified | Verified |
2 | Hardoi | Sursa | SIKANDARPUR | 413009 | BARBATAPUR | 110 | 110 | 100 | Har Gar Jal | Certified | Verified |
3 | Hardoi | Sursa | SIKANDARPUR | 413010 | MADHIYA SHUKLA | 83 | 83 | 100 | Har Gar Jal | Certified | Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 16 | 16 | Yes | 0 | NA | No | 8355.00 | 8355.00 |