Scheme Details
DISTRICT
Sitapur
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20013249
SCHEME NAME
Bahrimau water supply scheme
ESTIMATED COST
477.16
EXPENDITURE
295.72
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
35
Procured
35
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
22033.00
Meter
Length Laid
22033.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Kasmanda | Bahrimau | 411603 | Bahrimau | 742 | 742 | 100% | Har Ghar Jal | Certified |
| 2 | Sitapur | Kasmanda | Bahrimau | 411604 | Mahakhar | 159 | 159 | 100% | Har Ghar Jal | Certified |