Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Sitapur Larsen & Toubro Ltd 20013288 Rauwapur Newada water supply scheme 306.00 129.78 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
2 1 1 1 1 1 1 0 18 18 Yes 0 NA No 16591.00 16106.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Sitapur Sakaran Rauwapur Newada 411064 Chak Deoria 98 57 58 Work In Progress Not Certified
2 Sitapur Sakaran Rauwapur Newada 411065 Rauwapur 294 288 98 Work In Progress Not Certified