Scheme Details
DISTRICT Amethi
AGENCY Welspun Kaveri Infraprojects JV
SCHEME ID 20013372
SCHEME NAME Shivali Water Supply Scheme
ESTIMATED COST 266.84
EXPENDITURE 134.46
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 20
Procured 20 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 7188.00 Meter
Length Laid 7206.00 Meter

Scheme Assigned Villages

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Amethi Shukul Bazar Shivali 439133 Shivali 378 378 100% Har Ghar Jal Not Certified