Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Welspun Kaveri Infraprojects JV | 20013493 | Thana Gaddi | 427.92 | 138.32 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 37 | 37 | No | 0 | NA | No | 21782.00 | 21000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Kerakat | Thana Gaddi | 471276 | Devnath Pur | 46 | 46 | 100 | Har Gar Jal | Not Certified |
| 2 | Jaunpur | Kerakat | Thana Gaddi | 471277 | Arazi Thana Gaddi | 3 | 3 | 100 | Har Gar Jal | Not Certified |
| 3 | Jaunpur | Kerakat | Thana Gaddi | 471278 | Thana Gaddi | 624 | 620 | 99 | Work In Progress | Not Certified |