Scheme Details
DISTRICT
Pilibhit
AGENCY
PNC-SPML-JV
SCHEME ID
20013669
SCHEME NAME
PAREWA ANUP VILLAGE WATER SUPPLY SCHEME
ESTIMATED COST
239.55
EXPENDITURE
192.17
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
5991.00
Meter
Length Laid
5991.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Barkhera | Parewa Anup | 404966 | Parewa Anup | 531 | 531 | 100% | Har Ghar Jal | Certified |