Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | NCC Ltd. | 20013813 | UJJARPAR | 270.51 | 244.02 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 20 | 20 | Yes | 0 | NA | No | 13571.00 | 14179.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Gagha | Ujjarpar | 456559 | Ujjarpar | 168 | 168 | 100 | Har Gar Jal | Certified |
| 2 | Gorakhpur | Gagha | Ujjarpar | 456560 | Ramnagar | 4 | 4 | 100 | Har Gar Jal | Certified |
| 3 | Gorakhpur | Gagha | Ujjarpar | 456561 | Gajahara | 153 | 153 | 100 | Har Gar Jal | Certified |