DISTRICT Bareilly
AGENCY NCC Ltd.
SCHEME ID 20013938
SCHEME NAME KAINI SHIVNAGAR Water Supply Scheme
ESTIMATED COST 257.70
EXPENDITURE 174.54
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 19
Procured 19 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 7584.00 Meter
Length Laid 7584.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bareilly Majhgawan Kaini Shivnagar 403455 Kaini Shivnagar 363 362 100% Work In Progress Not Certified