Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Welspun Kaveri Infraprojects JV | 20014187 | Dinapur | 379.63 | 141.75 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 25 | 25 | No | 0 | NA | No | 21333.00 | 20722.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Barsathi | Chak Malai | 469994 | Malai | 153 | 151 | 99 | Work In Progress | Not Certified |
| 2 | Jaunpur | Barsathi | Chak Malai | 469995 | Mahamadpur Chak Hulash | 41 | 39 | 95 | Work In Progress | Not Certified |
| 3 | Jaunpur | Barsathi | Chak Malai | 469996 | Chak Malai | 80 | 78 | 98 | Work In Progress | Not Certified |
| 4 | Jaunpur | Barsathi | Dinapur | 469998 | Dinapur | 241 | 238 | 99 | Work In Progress | Not Certified |