| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Kannauj | VSA | 20014758 | SAUNSHARI GRAMIN PEYJAL YOJNA | 410.91 | 243.66 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 35 | 35 | Yes | 0 | NA | No | 13773.00 | 13773.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kannauj | Kannauj | Saunshari | 419287 | Saunshari | 419 | 419 | 100 | Har Gar Jal | Certified | 
| 2 | Kannauj | Kannauj | Saunshari | 419288 | Barkagawn Raja | 121 | 44 | 36 | Work In Progress | Not Certified | 
| 3 | Kannauj | Kannauj | Saunshari | 419289 | Rampurshadi | 67 | 67 | 100 | Har Gar Jal | Certified | 
| 4 | Kannauj | Kannauj | Saunshari | 419290 | Chhachhapur | 88 | 88 | 100 | Har Gar Jal | Certified | 
| 5 | Kannauj | Kannauj | Saunshari | 419291 | Wahidpur | 65 | 65 | 100 | Har Gar Jal | Certified |