Scheme Details
DISTRICT
Deoria
AGENCY
LC INFRA
SCHEME ID
20014825
SCHEME NAME
PIPRA PURAN GRAM PANCHAYT WATER SUPPLY SCHEME
ESTIMATED COST
179.04
EXPENDITURE
111.63
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
17
Procured
17
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
5393.00
Meter
Length Laid
4200.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Deoria | Bhaluani | Piprapuran | 459976 | Gadhawa | 86 | 55 | 64% | Work In Progress | Not Certified |
| 2 | Deoria | Bhaluani | Piprapuran | 459977 | Pipara Puran | 109 | 106 | 97% | Work In Progress | Not Certified |