Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | VSA | 20014947 | RASULPUR HABIBULLAH W/S SCHEME | 336.74 | 91.55 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Mohammadabad | Rasulpur Habibulla | 473614 | Rasulpur Habibulla | 335 | 327 | 98 | Work In Progress | Not Certified | Not Verified |
2 | Ghazipur | Mohammadabad | Rasulpur Habibulla | 473615 | Sonbarsa | 78 | 53 | 68 | Work In Progress | Not Certified | Not Verified |
3 | Ghazipur | Mohammadabad | Rasulpur Habibulla | 473616 | Saida Chak | 30 | 18 | 60 | Work In Progress | Not Certified | Not Verified |
4 | Ghazipur | Mohammadabad | Rasulpur Habibulla | 473617 | Rasulpur Ahmad | 35 | 30 | 86 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 25 | 25 | Yes | 0 | NA | No | 8942.00 | 8285.00 |