Scheme Details
DISTRICT
Etawah
AGENCY
Indian Hume Pipe
SCHEME ID
20015030
SCHEME NAME
Phoolpur
ESTIMATED COST
193.71
EXPENDITURE
147.81
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6788.00
Meter
Length Laid
6411.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etawah | Saifai | PHOOLAPUR | 419598 | PHOOLPUR | 250 | 250 | 100% | Har Ghar Jal | Certified |
| 2 | Etawah | Saifai | PHOOLAPUR | 419599 | SIYAPUR BABU | 75 | 66 | 88% | Work In Progress | Not Certified |
| 3 | Etawah | Saifai | PHOOLAPUR | 419600 | UMRAHI | 122 | 122 | 100% | Har Ghar Jal | Not Certified |