Scheme Details
DISTRICT
Bareilly
AGENCY
NCC Ltd.
SCHEME ID
20015178
SCHEME NAME
LAIKHERA water supply scheme
ESTIMATED COST
239.28
EXPENDITURE
150.80
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
22
Procured
22
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
5246.00
Meter
Length Laid
5200.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Nawabganj | Laikhera | 403851 | Laikhera | 441 | 441 | 100% | Har Ghar Jal | Not Certified |