Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bareilly | NCC Ltd. | 20015215 | KHOH water supply scheme | 233.13 | 41.63 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 19 | 19 | Yes | 0 | NA | No | 5378.00 | 5260.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Nawabganj | Khoh | 403919 | Khoh | 178 | 170 | 96 | Work In Progress | Not Certified |
| 2 | Bareilly | Nawabganj | Khoh | 403920 | Dhakia Sadat Ali | 117 | 111 | 95 | Work In Progress | Not Certified |
| 3 | Bareilly | Nawabganj | Khoh | 403921 | Milak Mohammadpur | 55 | 50 | 91 | Work In Progress | Not Certified |