Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Bareilly
AGENCY NCC Ltd.
SCHEME ID 20015215
SCHEME NAME KHOH water supply scheme
ESTIMATED COST 233.13
EXPENDITURE 58.32
AUTOMATION STATUS
Disconnected View Live Screen
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 19
Procured 19 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 5378.00 Meter
Length Laid 5260.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bareilly Nawabganj Khoh 403919 Khoh 178 170 96% Work In Progress Not Certified
2 Bareilly Nawabganj Khoh 403920 Dhakia Sadat Ali 117 111 95% Work In Progress Not Certified
3 Bareilly Nawabganj Khoh 403921 Milak Mohammadpur 55 50 91% Work In Progress Not Certified