Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | VSA | 20015363 | GULAL SARAI W/S SCHEME | 566.64 | 125.47 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Mardah | Gulal Sarai | 472663 | Gulal Sarai | 373 | 334 | 90 | Work In Progress | Not Certified | Not Verified |
2 | Ghazipur | Mardah | Gulal Sarai | 472664 | Kasba Goar | 149 | 141 | 95 | Work In Progress | Not Certified | Not Verified |
3 | Ghazipur | Mardah | Gulal Sarai | 472665 | Mirpur | 155 | 155 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 2 | 2 | 1 | 1 | 1 | 1 | 0 | 35 | 35 | Yes | 0 | NA | No | 18194.00 | 17858.00 |