Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Ghazipur VSA 20015372 SARAIBANDI W/S SCHEME 392.87 78.56 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
7 1 1 1 1 1 1 0 18 18 Yes 0 NA No 14038.00 13912.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Ghazipur Virno Sarai Bandi 472602 Salempur Gopal 73 67 92 Work In Progress Not Certified
2 Ghazipur Virno Sarai Bandi 472604 Gopalpur Salem 75 75 100 Har Gar Jal Not Certified
3 Ghazipur Virno Sarai Bandi 472605 Jamalpur 13 13 100 Har Gar Jal Not Certified
4 Ghazipur Virno Sarai Bandi 472606 Basant Patti 30 30 100 Har Gar Jal Not Certified
5 Ghazipur Virno Sarai Bandi 472608 Hridyapur 21 21 100 Har Gar Jal Not Certified
6 Ghazipur Virno Shekhpur 472610 Sarai Bandi 130 107 82 Work In Progress Not Certified
7 Ghazipur Virno Bharsar 697481 JAMALPUR 30 27 90 Work In Progress Not Certified