Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Approve By Agency Status Approve By EE Status Automation Status
1 Ghazipur VSA 20015571 HIRDHARPUR W/S SCHEME 379.43 104.21 Verified Verified Not Integrated

Scheme Assigne Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified Handed Over Villages
1 Ghazipur Sadat Hiradhar Pur 471998 Hiradhar Pur 115 84 73 Work In Progress Not Certified Not Verified
2 Ghazipur Sadat Hiradhar Pur 472000 Raj Dharpur 45 45 100 Har Gar Jal Not Certified Not Verified
3 Ghazipur Sadat Hiradhar Pur 472001 Almde Pur 73 73 100 Har Gar Jal Not Certified Not Verified
4 Ghazipur Sadat Hiradhar Pur 472002 Ghurepur 47 47 100 Har Gar Jal Not Certified Not Verified
5 Ghazipur Sadat Hiradhar Pur 472003 Bhavanipur 75 75 100 Har Gar Jal Not Certified Not Verified
6 Ghazipur Sadat Hiradhar Pur 472004 Chakmadho 1 1 100 Har Gar Jal Not Certified Not Verified
7 Ghazipur Sadat Hiradhar Pur 472005 Paharpur 103 103 100 Har Gar Jal Not Certified Not Verified

Scheme Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
7 1 1 1 1 1 1 0 21 21 NA 0 NA No 13518.00 46578.00