Scheme Details
DISTRICT
Ghazipur
AGENCY
VSA
SCHEME ID
20015748
SCHEME NAME
BIRBALPUR W/S SCHEME
ESTIMATED COST
412.03
EXPENDITURE
83.78
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
28
Procured
28
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
26028.00
Meter
Length Laid
26028.00
Meter
Scheme Assigned Villages
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Mardah | Birbalpur | 472726 | Birbalpur | 162 | 161 | 99% | Work In Progress | Not Certified |
| 2 | Ghazipur | Mardah | Birbalpur | 472727 | Sultanpur | 136 | 130 | 96% | Work In Progress | Not Certified |
| 3 | Ghazipur | Mardah | Birbalpur | 472728 | Shahpur | 43 | 43 | 100% | Har Ghar Jal | Not Certified |
| 4 | Ghazipur | Mardah | Birbalpur | 472729 | Rukkapur Ta. Sahabuddinpur | 99 | 85 | 86% | Work In Progress | Not Certified |