Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | NCC Ltd. | 20015828 | KUNIYA NAUABAD | 215.77 | 123.90 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 15 | 15 | Yes | 0 | NA | No | 7753.00 | 7657.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | Mirzapur | Kuniya Nauabad | 407535 | Kuniya Nauabad | 202 | 202 | 100 | Har Gar Jal | Certified |
| 2 | Shahjahanpur | Mirzapur | Kuniya Nauabad | 407536 | Mohammadpur Urf Jallapur | 111 | 111 | 100 | Har Gar Jal | Certified |
| 3 | Shahjahanpur | Mirzapur | Kuniya Nauabad | 407537 | GAHBRIA URF KUNDARI | 85 | 85 | 100 | Har Gar Jal | Certified |