Scheme Details
DISTRICT Bareilly
AGENCY NCC Ltd.
SCHEME ID 20016034
SCHEME NAME GULAB NAGAR water supply scheme
ESTIMATED COST 239.81
EXPENDITURE 178.24
AUTOMATION STATUS
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 15
Procured 15 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 6565.00 Meter
Length Laid 6493.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bareilly Bhuta Majhwa Hetram 404283 MASORA MOHANPUR 43 43 100% Har Ghar Jal Not Certified
2 Bareilly Bhuta Gulab Nagar 404284 Khimpura 66 46 70% Work In Progress Not Certified