Scheme Details
DISTRICT
Bahraich
AGENCY
PNC-SPML-JV
SCHEME ID
20016148
SCHEME NAME
SAUGAHANA PHAKHARPUR PWS
ESTIMATED COST
315.85
EXPENDITURE
174.62
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9193.00
Meter
Length Laid
9193.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bahraich | Phakharpur | Saugahana | 442373 | Saugahana | 409 | 404 | 99% | Work In Progress | Not Certified |