Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bareilly | NCC Ltd. | 20016429 | AMRAULI water supply scheme | 193.66 | 114.61 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 15 | 15 | Yes | 0 | NA | No | 4937.00 | 4850.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Majhgawan | Amrauli | 403483 | Amrauli | 242 | 242 | 100 | Har Gar Jal | Certified |
| 2 | Bareilly | Majhgawan | Amrauli | 403484 | Sutera | 55 | 55 | 100 | Har Gar Jal | Certified |