Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Sambhal
AGENCY SPML Infra
SCHEME ID 20016587
SCHEME NAME JALALPUR WATER SUPPLY SCHEME
ESTIMATED COST 239.83
EXPENDITURE 111.23
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 20
Procured 20 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 7611.00 Meter
Length Laid 7611.00 Meter

Scheme Assigned Villages

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Sambhal Junawai Jalalpur 401080 Jalalpur 233 233 100% Har Ghar Jal Not Certified
2 Sambhal Junawai Jalalpur 401081 Kaletha 227 224 99% Work In Progress Not Certified
3 Sambhal Junawai Jalalpur 401082 Bahmora 61 61 100% Har Ghar Jal Not Certified