Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Sambhal
AGENCY SPML Infra
SCHEME ID 20016593
SCHEME NAME BHULAWAI WATER SUPPLY SCHEME
ESTIMATED COST 242.22
EXPENDITURE 104.98
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 0
Procured 0 KW
Work Status NA
Electric
Required 25
Transformer Procured NA
Work Status No
Distribution Line
Total Length 8234.00 Meter
Length Laid 8234.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Sambhal Baniakhera Bhulawai 388717 Bhulawai 567 519 92% Work In Progress Not Certified
2 Sambhal Baniakhera Bhulawai 388718 Akbarpur Jamima Jarai 92 75 82% Work In Progress Not Certified