Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Bijnor
AGENCY LC INFRA
SCHEME ID 20016849
SCHEME NAME Lodhipur milk & Bair
ESTIMATED COST 290.39
EXPENDITURE 243.32
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 16
Procured 16 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 12067.00 Meter
Length Laid 12400.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bijnor Noorpur Lodipur Milk 387644 Lodipur Milk 425 425 100% Har Ghar Jal Not Certified
2 Bijnor Noorpur Ber 387647 Ber 209 209 100% Har Ghar Jal Not Certified
3 Bijnor Noorpur Ber 387648 Sharfuddin Nagar Urf Kaimri 114 114 100% Har Ghar Jal Not Certified