Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Larsen & Toubro Ltd | 20016953 | BASIPUR URF PIYARI_NINDOPUR W/S SCHEME | 387.40 | 249.05 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 7 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 25 | 25 | Yes | 0 | NA | No | 20231.00 | 18071.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Deokali | Nindopur | 472365 | Nindopur | 98 | 23 | 23 | Work In Progress | Not Certified |
| 2 | Ghazipur | Deokali | Nindopur | 472366 | Raddipur | 66 | 66 | 100 | Har Gar Jal | Not Certified |
| 3 | Ghazipur | Deokali | Nindopur | 472367 | Bharopur | 35 | 35 | 100 | Har Gar Jal | Not Certified |
| 4 | Ghazipur | Deokali | Nindopur | 472368 | Gopalpur | 6 | 1 | 17 | Work In Progress | Not Certified |
| 5 | Ghazipur | Deokali | Basipur Urf Piari | 472400 | Basipur Urf Piari | 281 | 281 | 100 | Har Gar Jal | Certified |
| 6 | Ghazipur | Deokali | Basipur Urf Piari | 472401 | Chak Budasen | 13 | 13 | 100 | Har Gar Jal | Certified |
| 7 | Ghazipur | Deokali | Basipur Urf Piari | 472402 | Chak Latiph | 13 | 13 | 100 | Har Gar Jal | Certified |