Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Larsen & Toubro Ltd | 20017063 | MAKHADUMPUR W/S SCHEME | 321.44 | 188.38 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Kasimabad | Makhdumpur | 473056 | Makhdumpur | 242 | 242 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Ghazipur | Kasimabad | Makhdumpur | 473057 | Daswantpur | 72 | 72 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Ghazipur | Kasimabad | Makhdumpur | 473059 | Karawana M. Makhdumpur | 138 | 138 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 21 | 21 | Yes | 0 | NA | No | 16015.00 | 15800.00 |