Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Larsen & Toubro Ltd | 20017134 | KANAKPUR | 146.26 | 97.54 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 11 | 11 | Yes | 0 | NA | No | 4670.00 | 4650.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Pindara | KANAKPUR | 475702 | Kanakpur | 143 | 142 | 99 | Work In Progress | Not Certified |
| 2 | Varanasi | Pindara | KANAKPUR | 475703 | Ratwarvegpur | 94 | 67 | 71 | Work In Progress | Not Certified |
| 3 | Varanasi | Pindara | KANAKPUR | 475704 | Kharka | 66 | 62 | 94 | Work In Progress | Not Certified |
| 4 | Varanasi | Pindara | KANAKPUR | 475705 | BHATBANDHA | 13 | 13 | 100 | Har Gar Jal | Not Certified |
| 5 | Varanasi | Pindara | KANAKPUR | 475706 | Bhudakuda | 8 | 5 | 62 | Work In Progress | Not Certified |