| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Deoria | Gayatri Projects LTD | 20017276 | MEDNAPUR GP WATER SUPPLY SCHEME | 409.60 | 239.54 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 31 | 33 | Yes | 0 | NA | No | 17883.00 | 17880.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Deoria | Baitalpur | Mednapur | 459412 | Medanapur Urf Bilaspur | 414 | 407 | 98 | Work In Progress | Not Certified |
| 2 | Deoria | Baitalpur | Mednapur | 459413 | Makohiyawa | 28 | 27 | 96 | Work In Progress | Not Certified |